Project Summary
This project was a complete bumper package, front and rear. 23 tools needed to produce 200 sets of parts.
DFM – The DFM review period was 3 days between our report and the client review. Common design issues identified and adjusted for.
DAY 1 – Project starts, client confirms drawings and mold fabrication begins.
WEEK 8 – Tooling complete, test parts run and shipped to client for review.
WEEK 9 – Client confirms test parts. Vowin runs 200 sets and ships to the client the same week.
SERVICE:Â Rapid Tooling Package & Low-Volume Injection Molding.
QUANTITY:Â 23 Tools – 200 Sets Of Parts
MATERIALS TOOLING:Â Steel 45
MATERIALS PARTS: ABS
FINISHING: Painting & Chrome
LEAD TIME:Â 10 Weeks
This rapid tooling project was all about capacity, timing, and execution.
In rapid manufacturing we are always adjusting so we can serve all our clients needs. Rapid manufacturing requires rapid scheduling adjustments at times.