Project Summary This project was a complete bumper package, front and rear. 23 tools needed to produce 200 sets of parts. DFM The DFM review period was 3 days between our report and the client review. Common design issues identified and adjusted for.




 

Project Summary

This project was a complete bumper package, front and rear. 23 tools needed to produce 200 sets of parts.

DFM – The DFM review period was 3 days between our report and the client review. Common design issues identified and adjusted for.

DAY 1 – Project starts, client confirms drawings and mold fabrication begins.

WEEK 8 – Tooling complete, test parts run and shipped to client for review.

WEEK 9 – Client confirms test parts. Vowin runs 200 sets and ships to the client the same week.

SERVICE:  Rapid Tooling Package & Low-Volume Injection Molding.

QUANTITY:  23 Tools – 200 Sets Of Parts

MATERIALS TOOLING: Steel 45

MATERIALS PARTS: ABS

FINISHING: Painting & Chrome

LEAD TIME: 10 Weeks

This rapid tooling project was all about capacity, timing, and execution.

In rapid manufacturing we are always adjusting so we can serve all our clients needs. Rapid manufacturing requires rapid scheduling adjustments at times.


  • Competitive

  • One to One Service

  • Enginner Review

  • Quality

  • Fast Delivery

  • Request Quote Right Now

  • Design

    Prototype

    Low Volume Production

    Mold

    Production

    Contact